This tracker is baselined on the Weekly Progress Update contract milestones (commencement 19 May, Practical Completion 30 June). SRG's Construction Methodology Rev 3.2 demonstrates how early mobilisation and re-sequencing build float and redundancy against those contract dates:
Where the methodology runs ahead of the contract baseline, the gap is deliberate redundancy. The contract milestones remain the reference baseline (PC 30 June); the working completion is re-baselined to 13 July (Rev 2.1) on the confirmed Company steel dates, with the delay captured under EOT-002. Current risks (Train 1 module rework, T2 steel-gated back end) are tracked against them.
| ID | Activity | Date | Week | Notes |
|---|
Wind bands are indicative planning guides only. Safe working wind limits for any lift are confirmed by the approved lift studies and the crane operator on the day.
| Activity | WBS | Status |
|---|---|---|
| Role | Name | Status |
|---|---|---|
| General Manager — SW | Mark Cowle | SRG Perm |
| Operations Manager | Joshua Toth | SRG Perm |
| HSET Superintendent | Haydyn Nissen | SRG Perm |
| Project Superintendent | Adam Riley | SRG Perm |
| Rope Access Supervisor (IRATA L3) | Jordan Kirkby | SRG Perm |
| Rope Access Technical Authority | Nathan Roberts-Tindall | SRG Perm |
| Fabrication Supervisor | Paul Berry | SRG Perm |
| HSE Advisor | Jacinta Jeffery | SRG Perm |
| QA/QC Engineer | Muhammad Ali | SRG Perm |
| Surveyor | BE Surveys | Subcontractor |
SMP Execution daily shift reports issued to the Covalent team, most recent first. Each entry captures the safety status, day-shift manning, progress against the modules and stack, forecast work and any concerns raised.
| Deliverable | Owner | Status | Document |
|---|---|---|---|
| Construction Methodology (Schedule B)Rev 3.2 · 21 May · sequence, hold points, lift-study integration | SRG | Complete | View Rev 3.2 ⭳ |
| Project WHS Management Plan (COV-MMP-0001)Rev 1.00 · signed 21 May | SRG HSE | Complete | View signed ⭳ |
| SWMS — high-risk construction workWorking at Heights, EWP, MHE, Rope Access, Cranes & Lifting | SRG HSE | Complete | 5 SWMS — see Safety Docs ↓ |
| Inspection & Test Plans (ITPs)Train 1 compiled ITPs in the submitted MDR — module assembly/installation, stack removal, flange, painting | SRG QA/QC | In MDR | Train 1 MDR — see QA/QC Docs ↓ |
| Lift Studies (LPA / Crane Corp)Cranecorp T1 Module 1 held; CCA-15-03/04 & 05/06 issued by LPA | Covalent / LPA | Complete | View T1 M1 ⭳ |
| Survey methodology + calibrationPre-erection, assembly-pad, progressive, pre-lift gate, as-built | BE Surveys | Complete | View Rev 2 ⭳ |
| Traffic Movement Plan (TMP)COV-TMP-0001 Rev 1.00 · crane radius, laydown access, pedestrian exclusion | SRG HSE | Complete | View Rev 1.00 ⭳ |
| Critical Risk Assessment / TBRATask-based risk assessment — SRG Global & Crane Corp, Stack Extension | SRG + Crane Corp | Complete | Download TBRA ⭳ |
| IRATA certification recordsAll L2/L3 technicians + Rope Access Technical Authority sign-off | SRG RA | Submitted | Held by Covalent |
| RapidCrews training-needs analysis100% competency compliance prior to mobilisation | SRG | Submitted | Held by Covalent |
Indicative crew roster for the stack works. D = day shift, N = night shift; blank = off. Scroll right for the full window.
Competency & ticket register for the site crew. A green tick marks a held ticket — click any tick to view the ticket for verification. Tickets are added as they are received from SRG.